Phases and weighting

Phases and weighting


Guide for using phases and weighting of phases on a tag



INNHOLDSFORTEGNELSE




Purpose


Phases enable organisation and step-by-step progression of projects and similar on a tag (individual, project or object).

The purpose is to phase tasks in order to keep track of progress.

From the overview it is also possible to export existing phases, make changes in the file and import again


Navigation to phases is under 'Settings - Phases'




The structure of the phases comes from the NORSOK Z-007 standard




Phases in use


From a tag (project, individual, object) you can add phases in a work process.

Each phase can be its own step in execution, for example a service or a project etc.





Weighting


The weighting of a phase determines how much impact its percentage completion has on the overall completion of the project.














Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article